47) During the six month update on a 1 year, $50,000 project, the analysis shows that the BCWS is $25,000; the BCWP is $20,000 and the ACWP is $15,000. What can be determined from these figures?
A. The project is behind schedule and over cost.
B. The project is ahead of schedule and under cost.
C. The project is ahead of schedule and over cost.
D. The project is behind schedule and under cost.
|
|