41) What is critical path?
A. The shortest path through the network, which represents the longest amount of time in which a project can be completed.
B. The path with zero float.
C. The longest path through the network, which represents the shortest amount of time in which a project can be completed.
D. The path with the most activities with the longest durations.
E. b and c
|
|