查看: 5600|回复: 5

標準工時對MRP的影響及Lead Time的推算邏輯

[复制链接]
论坛徽章:
76
生肖徽章:猪
日期:2007-09-26 12:35:55生肖徽章:猪
日期:2007-09-26 12:35:54生肖徽章:猪
日期:2006-12-25 21:31:05生肖徽章:猪
日期:2007-09-14 17:25:47生肖徽章:猪
日期:2006-09-07 17:08:46生肖徽章:猪
日期:2007-09-26 17:08:28生肖徽章2007版:猪
日期:2008-10-29 21:57:11生肖徽章2007版:猪
日期:2009-03-02 15:41:51ITPUB元老
日期:2008-05-26 11:03:14马上有车
日期:2014-02-18 16:41:11
跳转到指定楼层
1#
发表于 2004-8-12 08:40 | 只看该作者 回帖奖励 |倒序浏览 |阅读模式
[轉帖]

Oracle Manufacturing lead times Calculation and Setup (ZT)
This document serves as a guide to Oracle Manufacturing Lead times. It answers
the following questions:

1. How are lead times, in Oracle manufacturing applications, used?
2. How are lead times maintained?
3. How do lead times impact other processes?
4. How are lead times defined?

This document contains numerous facts and information on lead times used in 
Oracle Manufacturing Applications and is intended for anyone having a need to
setup or understand the functionality of Oracle Manufacturing Lead times.

1. BASIC MAINTENANCE.

a. The workday calendar must be setup correctly and rebuilt any time
modifications are made to the calendar.

Navigation paths: Bill of Materials/Setup/Calendars
Inventory/Setup/Organization/Calendars

b. Once modifications are made, rebuild the calendar by selecting the
special option on the top tool bar. On the drop down list, click on build.

c. Any time changes are made to a routing or resource, recalculate and
rollup the lead times.

Navigation path: Bill of Materials/Routings/Lead times


2. GENERAL FACTS

a. For an item to have manufacturing lead times calculated, it must be a
make item. Lead times are not calculated for purchased items even if they
have a routing.

1) Navigation path: Inventory/Items/Organization Items.
2) Select the General Planning alternate region.
3) Choose the make option for make or buy.

b. Set the scheduling option for the operation resources to yes.

1) Navigation path: Bill of Materials/Routings.
2) Put the cursor on the desired operation sequence.
3) Click on the [Operation Resources] button.
4) Select the desired resource sequence with your cursor.
5) Select the Scheduling alternate region.
6) Select the Yes option for schedule.

c. If using a fixed lead time for a resource, use a basis of Lot.

1) Navigation path: Bill of Materials/Routings.
2) Put the cursor on the desired operation sequence.
3) Click on the [Operation Resources] button.
4) Select the desired resource sequence with your cursor.
5) Select the Main alternate region.
6) Select the lot option for the basis.

d. If using want a variable lead time for a resource, use a basis of Item.

1) Navigation path: Bill of Materials/Routings.
2) Put the cursor on the desired operation sequence.
3) Click on the [Operation Resources] button.
4) Select the desired resource sequence with your cursor.
5) Select the Main alternate region.
6) Select the item option for the basis.

e. If a number other than 1 (the default) is entered in the assigned units
field, the scheduler will divide the lead time for that resource by the number
of assigned units for the resource entered and use the fractional lead time in
the lead time roll up. The assigned units field tells the scheduler how many
resources/machines are available to the job in order to complete it in less
time. In other words, if a 2 is entered, the lead time for this resource will
be cut in half. If you a 3 is entered, the lead time will be one third and so
on.

1) Navigation path: Bill of Materials/Routings.
2) Put the cursor on the desired operation sequence.
3) Click on the [Operation Resources] button.
4) Select the desired resource sequence with your cursor.
5) Select the Scheduling alternate region. Here you can change the
number of assigned resources that you want for this resource.

f. MRP expects that material due is received into inventory by the
beginning of the business day on which it is due. Consider
receiving it into inventory at the close of business on the previous day.
Simply change your receiving function to accommodate this.

g. MRP will use the fixed .
lead time if entered. This can be manually
entered into the organization item form in inventory.

Navigation path: Inventory/Items/Organization Items

h. Fixed lead time is automatically entered if the Lead time Rollup is done.
If the fixed lead time is manually entered, it will be over-written whenever a
lead time rollup is done.

i. When doing a lead time rollup, there is no validation for items if a
range of items is selected. If a specific item is selected, it validates
that item and, if it does not have a bill, it does not calculate any
lead times.

j. To set up a variable lead time for a resource that can complete
one unit every ten minutes:

1) Navigate to Bill of Materials/Routings/Routings.
2) Query up a routing.
3) Put the cursor on the desired operation.
4) Click on the [Operation Resources] button.
5) Enter the resource sequence and the name of the resource that
will do the work.
6) Make sure the Unit of Measure (UOM) that defaults is correct.
In almost all cases it should be hour (HR).
7) Select Item from the drop down menu for basis.
8) Enter six (6) in the Inverse column under rate or amount. The
system has now been told that six items per hour or one unit every ten minutes
can be completed.

k. Oracle WIP uses WIP Detailed Scheduling and Repetitive Line Scheduling
to determine order start date. Therefore, it is conceivable that MRP and
WIP could recommend different starting dates to meet the same requirement
due to the more refined method of order start date calculations in WIP.

l. Oracle starts calculating the lead time at 12:00AM or the start time
of the first defined shift for the day.

m. Oracle always counts idle time in the variable lead time calculations
because it uses a 24 hour day. Therefore, the lead time is expressed
as a decimal value of the 24 hour day. Calculations are based upon the
second.

n. Any time-based resource will be converted and rounded to the number of
seconds. The converted value has to be at least one second in order to be
calculated. The rounding to number of seconds is by design. For
non-time-based resources, the conversion rate is zero and will not have
any effect on lead time calculations. For example, WIP (the application
which actually does the calculation), converts a usage rate of .000018 of
an hour to .0648 seconds (.000018 x 3600 second in an hour) which is then
rounded to 0. The code will not work if the precision is below a second.
This is standard functionality.

o. When doing forward scheduling, you have to schedule the resource
based on the shift hours (using start and stop times), workdays and
non-workdays, the start date and time of the lot and the usage rate of the
resource. In doing this, any elapsed or idle time, due to a resource not
being available to work, will be added to the lead time. Depending on the
size of the lot being processed, you could have a wide variety of
completion dates and times. For example:

- You have a resource that can process one unit per hour and is
available from 8:00 to 4:00.
- A lot of three units will be moved to the next resource at 11:00.
The lead time for this lot is .125 days for this resource.
- A lot of 10 cannot be moved to the next resource until 10:00 the
next day. This lot will then have a lead time of 1.0833 days for
this resource.

p. Dynamic Lead time Offsetting is the estimation of the start date of an
order, operation or a resource, based on the order quantity, lead times and
the workday calendar. Depending upon the number of units, volume and usage
rate, the lead time could be rounded to zero.

q. Detailed Lead time Scheduling calculates jobs to the .
second based on
resource units available and the usage rates.

r. Using a lead time lot size greater than one will give a more accurate
variable lead time. It should reflect the average lot size that will be
processed.

s. The Available 24 Hours checkbox on the resource schedule will ignore
manufacturing calendar days off if checked.

1) Navigation path: Bill of Materials/Routings.
2) Put the cursor on the desired operation sequence.
3) Click on the [Operation Sequence] button.
4) Select the desired resource sequence with your cursor.
5) Select the Scheduling alternate region.

t. Repetitive Line Lead times include:

1) Fixed line or routing based lead times.
2) Processing lead time.

u. Calculating the Lead time of Purchased Items.

1) The workday calendar is not included when calculating any lead-
times for purchased items. It is assumed that the supplier is
a 24x7 operation in Releases 10.7 and 11.x.

2) The purchased items lead time is calculated as follows:

Postprocessing Lead time (time needed to move from receiving
to inventory)
+
Processing Lead time (time vendor needs the order before
delivery to your dock)
+
Preprocessing Lead time (purchase order preparation)

3) The results are:

The dock date (found on the Planning Detail Report) is the date
by which the vendor should deliver the material to your dock.

Dock Date = Order Due Date - Postprocessing Lead time

The start date is the date by which the sales
order should be given to the vendor.

Start Date = Dock Date - Processing Lead time

The order date is the date by which the purchase order should
be started.

Order Date = Start Date - Preprocessing Lead time

4) You can assign values for fixed lead time instead of assigning
the processing lead time.

v. Calculating the Lead time of Manufactured Items:

1) Fixed Lead time (time your shop floor needs to manufacture the
item or complete the job).

Fixed lead time =
lot time (usage rate or amount) / assigned units

2) Variable Lead time (time your shop floor needs to manufacture
each item - each piece * variable lead time)

Variable lead time =
total lot time + ((item based time * lot size) assigned units)

3) The planned order order date is the date by which you need to
start the process of creating a discrete job or repetitive line.
It is calculated as follows:

Planned order order date =
planned order order date - preprocessing lead time

4) The planned order due date is the date by which the item is needed.
It is similar to the dock date for a purchased item.

5) The planned order start date is the date by which you need to
release a discrete job or start a line. It is calculated as
follows:

Planned order start date =
planned order due date - lead time offset

The lead time offset is used as follows:

Planned order due date - lead time offset =
planned order order date

The lead time offset is calculated as follows:

Lead time offset =
Fixed Lead time + (Variable Lead time * Order Quantity)


3. MANUFACTURING LEADTIME CALCULATIONS.

a. For items that you plan and cost with the same lot size, you specify
a value only for the standard lot size.

b. For items that you.
plan with one lot size and cost with a different lot
size, you can specify a value for the lead time lot size. BOM then
calculates the manufacturing lead time for the item using this value as
opposed to the standard lot size.

c. If one item's routing references a common routing, set either the lead-
time lot size or standard lot size to the same value.

d. Primary routings are automatically updated with the lead times.

e. Offset percent is calculated for each resource on a routing operation
as the percent of processing lead time required from previous operations.
This is calculated from the start of the job to the start time of a resource
at an operation.

f. A value of zero is assigned to the fixed, variable and processing lead-
time of a manufactured item that does not have a routing and is not
assigned to a repetitive line.

g. Detailed scheduling is used to compute the fixed and variable lead-
times. BOM does not consider pre-processing when computing manufacturing
lead time.


4. CUMULATIVE MANUFACTURING LEADTIME CALCULATIONS.

a. BOM computes cumulative manufacturing lead times and cumulative lead-
time by stepping through the indented bill structure.

b. BOM sets an item's cumulative manufacturing lead time using the
following:

1) Manufacturing lead time for the item.
+
2) Maximum [(cumulative mfg lead time - offset days) for any
component in bill]


5. CUMULATIVE TOTAL LEADTIME CALCULATIONS.

a. BOM computes cumulative manufacturing lead times and cumulative lead-
time by stepping through the indented bill structure.

b. BOM sets an item's cumulative total lead time using the following:

1) Total lead time for the item.
+
2) Maximum [(cumulative total lead time - offset days) for any
component in bill]


6. ASSIGNING LEADTIMES.

Item Manufactured Purchased
Attribute Item Item
------------------------ ------------ ---------
Pre-processing Lead time You enter You enter
Processing Lead time BOM/ENG You enter
Post-processing Lead time N/A You enter
Cumulative Mfg Lead time BOM/ENG N/A
Cumulative Total Lead time BOM/ENG N/A
Lead time Lot Size You enter N/A


7. HOW TO ...?

a. In order to set up a fixed lead time for a resource that takes one
hour to complete:

1) Navigate to Bill of Materials/Routings/Routings.
2) Query up a routing.
3) Put your cursor on the desired operation.
4) Click on the operation resources button.
5) Enter the resource sequence and the name of the resource that will
do the work.
6) Make sure the Unit of Measure (UOM) that defaults is correct. In
almost all cases, it should be hour (HR).
7) Select Lot from the drop down menu for Basis.
8) Enter one (1) in the Inverse column under rate or amount. You
have now told the system that you can do one lot per hour.

b. In the Operation Resource form, in the Scheduling alternate region,
is a column called Offset Percent. This is the calculated percent of the
total manufacturing lead time that is completed by all of the previous
operations. For example, if all of the operations in the routing takes a
total of ten hours to complete, and the offset percent of a resource is 40%,

then this resource is started 4 hours after the start of the first
operation.

c. It should be noted that when the calculate lead time program is run, it
will use the BOM revision that you have entered for the routing you have
selected to calculate the lead time. Lead times are connected to the
routing and not to the.
bill of materials. When you run the lead time roll
up, it will use the revision of the bill of material that you have selected.
This is because the lead time roll up program uses the lead times of
subassemblies for which the lead time has been previously calculated.


8. GLOSSARY OF LEADTIME DEFINITIONS.

a. FIXED LEADTIME is the portion of lead time that is independent of
order quantity. This could be setups, teardown, batch processes or
anything else that requires time to do a lot. Fixed lead times for an item
can be entered manually.

1) Navigation path: Inventory/Items/Organization Items.
2) Select the Lead time alternate region for the item.
3) Enter the desired Fixed Lead time and save the form.

Please note that a manually entered lead time will be replaced by the
lead times generated by the Manufacturing Lead time rollup.

b. VARIABLE LEADTIME is the portion of lead time that is dependent upon
order quantity. It is the required time to produce one additional unit of
an assembly. The formula the system uses is:

[(End date - system date) - fixed lead time] + lead time lot size.

Variable lead times for an item can be entered manually.

1) Navigation path: Inventory/Items/Organization Items.
2) Select the Lead time alternate region for the item.
3) Enter the desired Variable Lead time and save the form.

Please note that a manually entered lead time will be replaced by the lead-
times generated by the Manufacturing Lead time rollup. The variable lead-
time is used in dynamic lead time offsets.

c. PRE-PROCESSING LEADTIME is the time required to release a purchase
order. It is used for Purchase orders, discrete jobs and repetitive lines.
It can include the requisition processing and any approval cycles
required. It can also be used for the time necessary to create internal
paperwork for a discrete job or repetitive line from the time you learn of
the requirement.

d. PROCESSING LEADTIME is the time required to purchase or manufacture
an item. It is computed as the time required to complete 1 lead time lot
size of an item. The formula for this includes the fixed and variable
portions of lead times.

end date (for job 2) - system date

BOM determines an item's lead time lot size from two item master fields:
Standard Lot Size and Lead time Lot Size.

e. POST-PROCESSING LEADTIME is the time it takes to receive, inspect
and move a buy part to inventory. You must physically enter
post-processing lead time for each purchased item.

f. CUMULATIVE MANUFACTURING LEADTIME is the time required to make an
assembly if all raw materials are in stock. This assumes that you must
manufacture every assembly, level by level. BOM automatically calculates
this value.

g. CUMULATIVE TOTAL LEADTIME is the time required to make an assembly if
no raw materials are in stock. This assumes that every raw material would
either have to be ordered or manufactured. BOM automatically calculates
this value.

h. TOTAL LEADTIME is the Fixed Lead time + (Variable Lead time * Order
Quantity)..
论坛徽章:
0
2#
发表于 2004-8-12 12:09 | 只看该作者
 好东东,谢谢。这是METLINK上的资料吗?

使用道具 举报

回复
论坛徽章:
13
生肖徽章2007版:蛇
日期:2008-04-07 19:50:192011新春纪念徽章
日期:2011-02-18 11:43:33ITPUB9周年纪念徽章
日期:2010-10-08 09:28:51生肖徽章2007版:羊
日期:2009-09-14 11:24:242009日食纪念
日期:2009-07-22 09:30:00授权会员
日期:2008-10-18 08:26:05生肖徽章2007版:鸡
日期:2008-10-11 11:00:40生肖徽章2007版:马
日期:2008-09-18 09:45:46奥运会纪念徽章:铁人三项
日期:2008-08-01 14:31:54数据库板块每日发贴之星
日期:2008-06-14 01:02:01
3#
发表于 2008-9-2 16:18 | 只看该作者
能翻译下就美了~

使用道具 举报

回复
论坛徽章:
9
ITPUB元老
日期:2011-12-24 19:00:09
4#
发表于 2008-9-11 15:05 | 只看该作者
多謝秀才

使用道具 举报

回复
论坛徽章:
6
2009新春纪念徽章
日期:2009-01-04 14:52:28祖国60周年纪念徽章
日期:2009-10-09 08:28:00ERP板块每日发贴之星
日期:2011-03-28 01:01:02蜘蛛蛋
日期:2011-11-12 23:23:432012新春纪念徽章
日期:2012-01-04 11:51:22福特
日期:2014-02-14 15:37:15
5#
发表于 2008-9-12 09:04 | 只看该作者
很不错,感谢秀才。呵呵

使用道具 举报

回复
论坛徽章:
5
授权会员
日期:2006-05-13 15:05:252008新春纪念徽章
日期:2008-02-13 12:43:03生肖徽章2007版:龙
日期:2009-09-10 11:23:34ITPUB十周年纪念徽章
日期:2011-11-01 16:20:28妮可·罗宾
日期:2020-09-14 14:10:48
6#
发表于 2008-9-12 19:41 | 只看该作者
google翻譯:


甲骨文制造业交货时间的计算和安装(锡ZT )
本文件服务为指导,甲骨文公司制造的前置作业时间。它的答案
以下问题:

1 。如何交货时间,在甲骨文制造业的申请,使用?
2 。如何带领时代维持?
3 。如何做时代的影响,导致其他进程?
4 。如何带领时代界定?

本文件载有无数事实和资料,对铅的时代所用的
甲骨文制造业的申请,并打算对任何人有需要
安装或了解的功能,甲骨文公司制造的前置作业时间。

1 。基本维修。

字母a.下班的日历,必须正确安装和重建,任何时间
修改作出日历。

导航路径:条例草案的材料/安装/日历
库存/安装/组织/日历

乙一旦修改,重建日历选择
特别选项,上方工具列。关于下拉列表中,单击关于建设。

长任何时间改变了路由或资源,重新计算和
汇总带头倍。

导航路径:条例草案的材料/路线/铅时代


2 。一般的事实

字母a.一个项目有制造业带头倍计算,它必须是一个
作项目。交货时间不计算购买的物品,即使他们
有一个路由。

1 )导航路径:库存/项目/组织项目。
2 )选择的总体规划候补地区。
3 )选择作出选择,作出或购买。

乙设置调度方案的运作资源,以肯定的。

1 )导航路径:条例草案的材料/路线。
2 )把光标对理想的操作序列。
3 )点击[运作资源]按钮。
4 )选择所需的资源序列与您的光标。
5 )选取调度候补地区。
6 )选择是选择附表。

长如果使用一个固定的时间,是一种资源,使用的基础上很多。

1 )导航路径:条例草案的材料/路线。
2 )把光标对理想的操作序列。
3 )点击[运作资源]按钮。
4 )选择所需的资源序列与您的光标。
5 )选择的主要候补地区。
6 )选择有很多选择的基础上。

四如果要使用一个变量的筹备时间是一种资源,使用的基础项目。

1 )导航路径:条例草案的材料/路线。
2 )把光标对理想的操作序列。
3 )点击[运作资源]按钮。
4 )选择所需的资源序列与您的光标。
5 )选择的主要候补地区。
6 )选择项目选择的基础上。

e.如果一些其他超过1 (默认值)是在进入指定的单位
场,调度会鸿沟带头的时间,资源由数量
分配单位为资源进入和使用分数的时间,
筹建时间,卷起来。指定的单位实地告诉调度多少
资源/机器可向就业,以完成它在不到
时间。在其他换句话说,如果一个2输入,带头的时间,这将资源
被削减了一半。如果您一进入三是,带头的时间将三分之一等
在…之上。

1 )导航路径:条例草案的材料/路线。
2 )把光标对理想的操作序列。
3 )点击[运作资源]按钮。
4 )选择所需的资源序列与您的光标。
5 )选取调度候补地区。在这里您可以改变
人数分配的资源您要为这一资源。

楼MRP的预计,由于材料是收到到存货所
开始营业日上,这是因为。考虑
接收到的库存在营业时间结束前一天。
简单地变更您的接收功能,以容纳这一点。

g. MRP的将使用固定的。
铅如果进入的时间。这可以手动
进入项目组织形式,在存货中。

导航路径:库存/项目/组织项目

每小时固定的时间自动进入,如果筹建时间,汇总工作要做。
如果固定的时间是手动进入,这将是过度的书面每当
筹建时间汇总工作要做。

我。时,做了带头的时间汇总,是没有验证的项目,如果一
多个项目被选中。如果一个具体项目是选定的,它验证
该项目的,如果没有一个条例草案,这并不计算任何
前置作业时间。

j.成立一个变量的时间,资源,可以完成
一个单位,每10分钟:

1 )浏览到条例草案的材料/路线/路线。
2 )查询了一个路由。
3 )把光标在理想的运作。
4 )按一下[运作资源]按钮。
5 )输入资源的顺序和名称的资源
做这项工作。
6 )确保计量单位( uom )默认是正确的。
在几乎所有情况下,应该小时(人力资源) 。
7 )选择项目从下拉菜单中为基础。
8 )进入6 ( 6 )在逆栏下的利率或金额。那个
系统现在已被告知, 6个项目,每小时或一个单位,每10分钟
可以完成。

k.甲骨文制品用途制品的详细调度和重复的在线调度
为了确定开始日期。因此,这是可以想象的MRP和
制品可建议不同的开始日期,以满足相同的规定
由于要更精确的方法,以便开始日期计算在制品。

研究甲骨文开始计算的筹建时间在上午12时或开始时间
的第一所界定的转移为天。

米。甲骨文总是算数的空闲时间在变铅时间计算
因为它使用24小时的一天。因此,筹建时间,是表示
作为一个十进制值24小时天。计算所依据的
第二。

12月31日任何时间为基础的资源将被转换,并四舍五入到人数
秒。转换价值要至少一秒,为了要
计算出来的。四舍五入到多少秒是由设计。为了
非基于时间的资源,转换率是零,不会有
任何影响,对铅的时间计算。举例来说,在制品(应用
这实际上是否计算) ,转换的使用率0.000018的
一个小时0.0648秒( 0.000018 x 3600秒在一个小时) ,然后
四舍五入到零。程式码将不会工作,如果精度是低于1秒。
这是标准的功能。

澳时,做了调度,你必须附表资源
的基础上,转变小时(使用启动和停止倍) ,工作日和
非工作日,开始的日期和时间,该地段和使用率的
资源。这样做,任何过去了,或空闲时间,由于资源的不
正在提供给工作,将被添加到筹建时间。视乎有关
大小该地段正在处理中,你可以有各种各样的
完成的日期和时间。例如:

-你是否有资源可以进程的一个单位,每小时是
可从8点至4点。
-大量的三个单位将迁往未来的资源在1 1:00。
带头的时间,这是很多0.125天为这一资源。
-很多1 0,无法移动到未来的资源,直到1 0点了
第二天。这很多届时将有带头作用的时间一点〇八三三天为
这一资源。

体育动态的时间足以抵销是估计的起始日期一
秩序,经营或资源的基础上,订购数量,交货时间和
下班的日历。取决于单位数目,体积和使用
率,筹建时间,可四舍五入后为零。

问:详细时间,调度计算的就业机会。
第二次的基础上
资源单位和使用率。

r.使用时间,很多尺寸大于1 ,将提供更准确
变导时间。它应反映的平均很多的大小将
处理中。

第可用24小时的复选框,对资源的附表,将不理会
制造业日历天,如果检查。

1 )导航路径:条例草案的材料/路线。
2 )把光标对理想的操作序列。
3 )点击[操作序列]按钮。
4 )选择所需的资源序列与您的光标。
5 )选取调度候补地区。

汤匙重复线带头时代,包括:

1 )固定电话线或基于路由的前置作业时间。
2 )处理的时间。

美国计算铅的时间购买的物品。

1 )下班的日历是不包括在计算任何铅
时代购买的物品。这是假定供应商
1 24x7运作,在新闻稿10.7和11.x.

2 )购买的物品导致的时间计算方法如下:

后导致的时间(所需的时间从接收
库存)
+
处理的时间(时间,供应商的需要,该命令之前,
交付给您的船坞)
+
预处理的时间(采购订单的制备)

3 )的结果是:

被告席上的日期(发现对规划详细报告)是日期
其中供应商应提供的材料到您的船坞。

船坞日期=为了在到期日-后导致时间

该起始日期,其中销售
为了应考虑到供应商。

开始日期=船坞日期-处理的时间

该命令日期,其中采购订单应
开始。

订单日期=起始日期-预处理导致时间

4 )您可以指定值为固定时间,而不是指派
加工筹建时间。

五,计算时间,导致制成品的项目:

1 )固定的时间(时间,您的车间需要制造
项目或完成的工作) 。

固定的时间=
很多时间(使用率或金额) /指派单位

2 )变导时间(时间,您的车间需要制造
每个项目-每一块*变导时间)

变导时间=
总有很多时间+ ( (项目基于时间*很多大小)指定单位)

3 )计划,以便秩序的日期由您需要
启动的过程中创造一个离散的工作或重复路线。
这是计算方法如下:

计划,以便订购日期=
计划,以便订购日期-预处理导致时间

4 )计划,以便因日期,其中该项目是必要的。
这是类似的被告席上的日期为购买项目。

5 )计划,以便起始日期由您需要
释放出一个离散的工作或开始一个路线。它的计算方法
如下:

为了计划的开始日期=
计划,以便在到期日-铅时间偏移

带头的时间是用来抵消如下:

计划,以便在到期日-铅时间偏移=
计划,以便订购日期

带头时间偏移的计算方法如下:

导致时间偏移=
固定的时间+ (变导时间*订购数量)


3 。制造业的交货期计算。

字母a.为您的项目计划和费用与同地段的大小,您所指定的
值只适用于标准很多大小。

乙为您的项目。
计划与一很多尺寸和成本与不同的地段
大小,您可以指定一个值为筹建时间,很多的大小。 BOM表,然后
计算制造业的时间,该项目使用此值作为
反对的标准有很多大小。

长如果一个项目的路由参考一个共同的路由,设置,无论是铅
时间很多的大小或标准很多大小相同的值。

四小学路线,自动更新与交货时间。

e.抵销%计算为每个资源的路由运作
作为%的加工所需的时间从以前的行动。
这是计算从一开始的工作,开始的时间资源
在一项行动中。

楼一值为零,是分配给固定,可变和加工铅
时间,一个制造项目,没有一个路由和不
分配到一个重复的路线。

g.详细的日程安排是用来计算的固定和可变铅
倍。 BOM的不考虑前处理时,电脑制造
筹建时间。


4 。累积制造业的交货期计算。

字母a. BOM的计算累积制造业交货时间和累积铅
时间,加强对通过缩进条例草案的结构。

乙BOM的树立了一个项目的累积制造业带头的时间使用
以下内容:

1 )制造的时间,该项目。
+
2 )最高[ (累计制作所导致的时间-抵销天)的任何
在条例草案的组成部分]


5 。累计交货期计算。

字母a. BOM的计算累积制造业交货时间和累积铅
时间,加强对通过缩进条例草案的结构。

乙BOM的树立了一个项目的累计总铅的时间使用下列内容:

1 )总铅的时间了该项目。
+
2 )最高[ (累计总数的时间-抵销天)的任何
在条例草案的组成部分]


6 。指派leadtimes 。

项目制品购买
属性项目项目
------------------------ ------------ ---------
前处理时间,您输入您所输入的
处理时间, BOM的/英您所输入的
后处理的时间n /一您所输入的
制作所导致的累积时间的BOM /英n / 1
累计筹建时间的BOM /英n / 1
带头的时间很多大小您所输入的n / 1


7 。如何... ?

字母a.在以建立一个固定的时间,资源,需时1
个小时才能完成:

1 )浏览到条例草案的材料/路线/路线。
2 )查询了一个路由。
3 )把您的光标移动对理想的运作。
4 )按对运作资源按钮。
5 )输入资源的顺序和名称的资源,将
做这项工作。
6 )确保计量单位( uom )默认是正确的。在…内
几乎所有情况下,应该小时(人力资源) 。
7 )选择有很多从下拉菜单中为基础。
8 )输入1 ( 1 )在逆栏下的利率或金额。您
现在告诉系统你可以做一很多每小时。

乙在行动中资源的形式,在调度候补地区,
是一栏,所谓抵销% 。这是计算%的
占制造业总铅的时间完成所有的前
行动。例如,如果所有的行动中,路由需
共有十个小时才能完成,并抵消%的资源是40 % ,

然后这个资源是开始4小时后开始第一
运作。

长应该指出的是,当计算时间,程序运行,它
将使用BOM的修改,您已进入为路由你有
选定计算的筹建时间。交货时间都连接到
路由,而不是向。
条例草案的材料。当您运行的筹建时间轧辊
起来,它会使用的修订条例草案的材料,您所选择的。
这是因为筹建时间,卷起来的计划使用,带头倍
组件为筹建时间,先前已计算出来的。


8 。词汇交货期的定义。

字母a.固定的交货期是部分时间,这是独立
订购数量。这可能是设置,拆解,或间歇过程
其他任何需要时间做的工作很多。固定时间为一个项目
可以手工输入。

1 )导航路径:库存/项目/组织项目。
2 )选择的筹建时间候补地区的项目。
3 )输入想要固定的时间和保存的形式。

请注意,手动进入筹建时间将所取代
铅时代所产生的制造业导致时间汇总。

乙可变的交货期是部分铅的时间取决于
订购数量。这是需要时间来产生一个额外的股
一大会。公式该系统采用的是:

[ (结束日期-系统日期) -固定的时间]+筹建时间很多的大小。

变导时代的一个项目,可以进入手动。

1 )导航路径:库存/项目/组织项目。
2 )选择的筹建时间候补地区的项目。
3 )输入想要的变量导致时间和保存的形式。

请注意,手动进入筹建时间将所取代铅
时代所产生的制造业导致时间汇总。变铅
时间是用在动态的时间偏移。

长前处理的交货期是所需的时间,释放出一个购买
命令。这是用于采购订单,离散的工作和重复的线路。
它可以包括征用加工和任何审批周期
必需的。它也可用于所需的时间,创造内部
文件为一个离散的工作或重复的路线,从时间,您了解的
有关规定。

四加工的交货期是所需的时间,购买或制造
一个项目。这是计算所需的时间,完成一时间,很多
大小的一个项目。公式为这包括固定和可变
部分的前置作业时间。

结束日期(为求职2 ) -系统日期

BOM的确定项目的时间,很多的大小从两个项目硕士领域:
标准很多的大小和时间,导致很多的大小。

e.后处理的交货期是所花费的时间接受检查
并提出购买部分库存。您必须身体进入
后处理的时间为每个购买的项目。

楼累积制造业的交货期是所需的时间作出一
大会如果所有原料的股票。这个假设您必须
制造每一个大会,层层。 BOM的自动计算
此值。

g.累计交货期是所需的时间,使一,如果大会
没有原材料是在股市。这个假设每原料会
要么被饬令或制造的。 BOM的自动计算
此值。

每小时总的交货期是固定的时间+ (变导时间*秩序
数量) ..

使用道具 举报

回复

您需要登录后才可以回帖 登录 | 注册

本版积分规则 发表回复

TOP技术积分榜 社区积分榜 徽章 团队 统计 知识索引树 积分竞拍 文本模式 帮助
  ITPUB首页 | ITPUB论坛 | 数据库技术 | 企业信息化 | 开发技术 | 微软技术 | 软件工程与项目管理 | IBM技术园地 | 行业纵向讨论 | IT招聘 | IT文档
  ChinaUnix | ChinaUnix博客 | ChinaUnix论坛
CopyRight 1999-2011 itpub.net All Right Reserved. 北京盛拓优讯信息技术有限公司版权所有 联系我们 未成年人举报专区 
京ICP备16024965号-8  北京市公安局海淀分局网监中心备案编号:11010802021510 广播电视节目制作经营许可证:编号(京)字第1149号
  
快速回复 返回顶部 返回列表