不得不觉得自己E文真的很菜,连着两道都被ISACA耍
109、An IS auditor should be concerned when a telecommunication analyst:
A、monitors systems performance and tracks problems resulting from program changes.
B、reviews network load requirements in terms of current and future transaction volumes.
C、assesses the impact of the network load on terminal response times and network data transfer rates.
D、recommends network balancing procedures and improvements.
NOTE: The responsibilities of a telecommunications analyst include reviewing network load requirements in terms of current and future transaction volumes (choice B), assessing the impact of network load or terminal response times and network data transfer rates (choice C), and recommending network balancing procedures and improvements (choice D). Monitoring systems performance and tracking problems as a result of program changes (choice A) would put the analyst in a self-monitoring role.
The correct answer is A.
An IS auditor should be concerned when a telecommunication analyst。。。
165. Assumptions while planning an IS project involve a high degree of risk because they are:
A. based on known constraints.
B. based on objective past data.
C. a result of a lack of information.
D. often made by unqualified people.
Assumptions are made when adequate information is not available. When an IS project manager makes an assumption, there is a high degree of risk because the lack of proper information can cause unexpected loss to an IS project. Assumptions are not based on "known" constraints. When constraints are known in advance, a project manager can plan according to those constraints rather than assuming the constraints will not affect the project. Having objective data about past IS projects will not lead to making assumptions, but rather helps the IS project manager in planning the project. Hence, if objective past data are available and the project manager makes use of them, the risk to the project is less. Regardless of whether they are made by qualified people or unqualified people, assumptions are risky.
The correct answer is C.
Assumptions while planning an IS project involve a high degree of risk because they are:
唉。。。
[ 本帖最后由 appppa 于 2008-6-4 22:59 编辑 ] |
|