原因是你在mrp2里面维护了 in-house production time。但是很不幸,这个影响,在plan order的Order finish date in the planned order里面没有提及。
不过你在production order的Basic finish date里面可以查到详细的说明。特别是它所提的example。
Example
The last operation of an order was completed on Thursday at 5 pm (17:00 hours). No float after production was maintained for the order.
If an in-house production time greater than 0 days is maintained in the material master record, the order finish date is Friday.
If an in-house production time of 0 days is maintained in the material master record, the order finish date is Thursday.
|
|